Glossary term
Monte Carlo Simulation
Subject: Risk Management, Risk Assessment and Quantification
Also known as: Monte Carlo method
Monte Carlo simulation is a technique that runs thousands of trials with randomly drawn inputs to show the range of possible outcomes and how likely each one is.
Explanation
Some risks are too complex for a simple formula. Monte Carlo avoids the problem by experiment. The analyst describes each uncertain input with a probability distribution, for example interest rates, project costs or loss sizes, and links them in a model. A computer then draws random values for each input, calculates the result, and repeats this thousands or millions of times. The collected results form a distribution, from which one can read the average, the worst 1% and the chance of missing a target. It is used for market risk, credit portfolios, operational risk capital, project schedules and pension funding. Results are only as good as the assumed distributions and the links between inputs, and correlations are easily misjudged. Decision makers see the spread of outcomes rather than a single best guess, and can size reserves to the odds.
Example
A construction firm is unsure about the cost of a large project because steel prices, labour rates and delays all vary. It builds a model with a range for each and runs 10,000 trials. The output shows a 20% chance of overspending the budget, so management adds a contingency reserve.
Not to be confused with
- Scenario Analysis
- Scenario analysis studies a few chosen stories in depth. Monte Carlo samples thousands of random combinations to map a whole range of outcomes.